Building Steps
Decisions
Pre building
- RPR
- Site inspection
- Lot coverage
- Utilities locations
- Permits - obtained by PK Builders
Lot preparation
- Demolition - if necessary
- Tree removal - if necessary
Concrete
- Organic material removed
- 4" of compacted fill used for base
- All concrete to be 32 mpa
- Concrete to be 4" thick and 6" thick on sides with 10 mm rebar on 16" o/c
Structure
- Framing inc trusses
- Sheathing - roof + walls
Finishing
- Overhead door
- Man door and windows
- Siding, soffits and fascia
- eavestroughs
Electrical
- 2 interior lights, 3 exterior lights
- 4 interior plugs, 1 exterior gfi, 2 interior switches
- Trenching if required
Interior finishing
- Drywall - if required
- Insulation - if required
Inspections
Site Clean Up