Building Steps

Decisions


Pre building

  • RPR
  • Site inspection
  • Lot coverage
  • Utilities locations
  • Permits - obtained by PK Builders

Lot preparation

  • Demolition - if necessary
  • Tree removal - if necessary

Concrete

  • Organic material removed
  • 4" of compacted fill used for base
  • All concrete to be 32 mpa
  • Concrete to be 4" thick and 6" thick on sides with 10 mm rebar on 16" o/c

Structure

  • Framing inc trusses
  • Sheathing - roof + walls

Finishing

  • Overhead door
  • Man door and windows
  • Siding, soffits and fascia
  • eavestroughs

Electrical

  • 2 interior lights, 3 exterior lights
  • 4 interior plugs, 1 exterior gfi, 2 interior switches
  • Trenching if required

Interior finishing

  • Drywall - if required
  • Insulation - if required

Inspections

  • Final garage inspection

Site Clean Up